The CEO Water, Andres Martinez, oversaw today the completion of construction of the pumping station in the hamlet of Las Pullas, in the municipality of Alguazas, who have had a budget of 238,000 euros, which will serve a population of 1,700 equivalent inhabitants.
These works have involved the construction of a pumping station and a drive that is connected with the collector of Saladar and ultimately with the filter of Ceuta.
The pumping station has two submersible pumps with shredder function, with frequency and another with static start a flow rate of 8.33 liters per second.
The drive has a pipe of 561 meters long.
The performance, co-funded through the European Cohesion Fund, is part of the objectives set by the Council in the II General Plan of cleansing and purifying of the Region of Murcia 2015-2020, which aims to incorporate all urban areas to regional system debug the region.
Source: CARM